Field descriptions: WIP schedule project fields

Summary

Descriptions of the fields in the Summary section
Field Description
Period name The name of the reporting period on which the WIP schedule is based. WIP schedules are based on the reporting periods set up in the top level of your company.
Period end The ending date of the WIP schedule's reporting period.
Comment Enter a comment about the WIP schedule.
End of year WIP schedule

The end of year WIP schedule for the prior year. You can drill down to view it.

If there's an end of year WIP schedule, it's used to determine YTD values in the current WIP schedule (such as YTD billed and YTD earned).

If there isn't an end of year WIP schedule, YTD values are the same as job to date values.

State Indicates whether the WIP schedule is posted or unposted.
Prior period WIP schedule

The WIP schedule for the prior reporting period. You can drill down to view it.

When you create a new WIP schedule, PM and CFO forecasts from the prior period WIP schedule are automatically copied into the new WIP schedule. If there isn't a prior period WIP schedule, PM and CFO forecasts are blank.

You can always reset PM and CFO forecasts to those from the prior period using the buttons Update CFO values with CFO values from prior period and Update PM values with PM values from prior period.

Values from the prior period WIP schedule are also used to determine some other values for the current period (such as Period costs and Period billings).

If there is a prior period WIP schedule, the Prior period section appears and shows information from the prior period WIP schedule.

Last refresh

The date and time that the WIP schedule was last updated with the latest project data and any changes to which projects are included in the WIP schedule.

To get the latest project data, edit the WIP schedule, and select Refresh. When you refresh, the WIP schedule is saved automatically.

Overview tab

The Overview tab shows the WIP projects grid. You can select multiple projects and use the buttons above the grid to update the selected projects at the same time.

Each project in the WIP projects grid shows totals for itself plus any subprojects that are included as part of it. If no subprojects are included as part of it, it shows data only for itself.

Buttons above the grid

Descriptions of the buttons above the grid on the Overview tab
Button Description
Finalize Select this button to mark the selected projects as finalized.
Update CFO values with PM values

For each selected project, replaces the current CFO forecasts with the current PM forecasts.

  • CFO forecast cost to complete is updated with PM forecast cost to complete
  • CFO forecast cost at completion is updated with PM forecast cost at completion
  • CFO forecast pct complete (%) is updated with PM forecast pct complete (%)
  • CFO forecast contract value is updated with PM forecast contract value
Update PM values with project values

For each selected project, replaces the current PM forecasts with values taken from the project contract and estimates for the project.

  • PM forecast cost to complete is updated with estimated cost to complete
  • PM forecast cost at completion is updated with total revised estimate
  • PM forecast pct complete (%) is updated with estimated percentage complete
  • PM forecast contract value is updated with total contract value
Clear CFO values

For each selected project, clears the following fields:

  • CFO forecast cost to complete
  • CFO forecast cost at completion
  • CFO forecast pct complete (%)
  • CFO forecast contract value
Clear PM values

For each selected project, clears the following fields:

  • PM forecast cost to complete
  • PM forecast cost at completion
  • PM forecast pct complete (%)
  • PM forecast contract value
Set project costs to complete (100%)

For each selected project, copies the job to date costs to CFO forecast cost at completion, which causes the CFO forecast percent complete to be calculated as 100%.

This button lets you easily update forecasts to show that a project is complete in terms of costs.

If you set both costs and billings to complete, the Job to date overbilled and Job to date underbilled fields show zero.
Set billings to complete (100%)

For each selected project, copies the job to date billings to CFO forecast contract value, indicating that everything for the job has been billed.

This button lets you easily update forecasts to show that a project is complete in terms of billings.

If you set both costs and billings to complete, the Job to date overbilled and Job to date underbilled fields show zero.
Update CFO values with CFO values from prior period

For each selected project, replaces the current CFO forecasts with the CFO forecasts from the prior period's WIP schedule.

The following fields are updated:

  • CFO forecast cost to complete
  • CFO forecast cost at completion
  • CFO forecast pct complete (%)
  • CFO forecast contract value
Update PM values with PM values from prior period

For each selected project, replaces the current PM forecasts with the PM forecasts from the prior period's WIP schedule.

The following fields are updated:

  • PM forecast cost to complete
  • PM forecast cost at completion
  • PM forecast pct complete (%)
  • PM forecast contract value
Unfinalize Select this option to change the Finalized field from Yes to No for the selected projects.

Fields in the grid

Descriptions of the fields in the projects grid on the Overview tab
Field Description
Project The project ID and description.
Errors

If there are one or more errors in the project data, the number of errors appears in this field.

Select the number to view the errors. You can save the WIP schedule with errors, but you must correct the errors before posting it.

Warnings

If there are one or more issues in the project's data related to the WIP schedule, the number of issues appears in this field.

Select the number to view the warnings. You can save or post the WIP schedule without addressing the warnings.

Project manager

The project manager assigned to the project.

Estimated cost to date

This amount comes from estimate entries in the project's primary estimate. Estimate entries are included if they meet the following criteria:

  • Have a workflow type of original, revision, or approved change

  • Have an effective date that falls before or on the end date for the WIP schedule

    If the estimate entry does not have a date, the estimate date is used instead.

Total contract value

This amount comes from all project contract lines linked to the project. The amount is the sum of the price for all project contract lines, including any change request entries linked to the project contract line through a change order.

A project contract line entry is included in the calculation if it meets the following conditions:

  • The workflow type is original or revision.

  • The price effective date is earlier than or on the end date of the WIP schedule period.

A change request entry within the same project contract line is included in the calculation if it meets the following conditions:

  • The workflow type is original, revision, or approved change.

  • The price effective date is earlier than or on the end date of the WIP schedule period.

CFO forecast cost at completion

You can enter an amount in this field, or it will be automatically calculated if an amount is entered in one of the following fields:

  • CFO forecast cost to complete

  • CFO forecast pct complete (%)

Those two fields are recalculated if an amount is entered in this field.

CFO forecast contract value

Enter the forecast contract value.

Job to date costs

The project's actual costs to-date.

This amount comes from journal postings to the cost accounts selected in the WIP management section of Configure Projects.

Journal entries are included in this amount if they meet the following conditions: 

  • The account is selected in the Cost accounts list in Configure Projects.

  • The project dimension assigned to the journal entry matches the WIP project or one of its child projects.

  • The entry date for the journal entry falls before the WIP schedule period-end date.

A debit amount posted to the account is added to the Job to date costs amount. A credit is subtracted.

Job to date billings

This amount comes from journal postings to the revenue accounts selected in the WIP management section of Configure Projects.

Journal entries are included in this amount if they meet the following conditions:

  • The account is selected in the Revenue accounts list in Configure Projects.

  • The project dimension assigned to the journal entry matches the WIP project or one of its child projects.

  • The entry date for the journal entry falls before the WIP schedule period end date.

A credit amount posted to the account is added to the Job to date billed amount. A debit is subtracted.

CFO forecast pct complete (%)

Enter your estimate of how much of the project has been completed.

If a value has been entered in the CFO Forecast cost at completion field, this field is calculated as follows:

Job to date costs / CFO forecast cost at completion

Earned to date

The amount in this field is calculated as follows:

CFO forecast contract value * CFO forecast pct complete (%)

This amount reflects the earnings going back to the beginning of the project; it is not limited to the current year.

YTD billed

The amount in this field is calculated as follows:

The total revenue from General Ledger entries for the project from the start of the current fiscal year to the WIP schedule period-end date.

YTD earned

The amount in this field is calculated as follows:

Earned to date - Earned to date as of the end of the prior year (take from the prior year EOY WIP schedule)

Job to date overbilled

If the Job to date billings amount is more than the Earned to date amount, this field displays the difference. Otherwise, the amount is zero.

If this field displays an amount other than zero, the same amount is displayed in the Overbilled or underbilled field.

The amount in this field is calculated based on the whole history of the project.

Job to date underbilled

If the Job to date billings amount is less than the Earned to date amount, this field displays the difference. Otherwise, the amount is zero.

If this field displays an amount other than zero, the same amount is displayed in the Overbilled or underbilled field.

The amount in this field is calculated based on the whole history of the project.

Comment Enter a comment about the project.
Finalize

Select Yes if you have finished modifying this project. All project rows must be finalized before posting the WIP schedule.

If a data refresh changes a calculated value for a project marked as Finalized, this field is automatically reset to No for that project.

Total revised estimate

This amount comes from estimate entries in the project's primary estimate.

Estimate entries are included if they have a workflow type of original, revision, or approved change.

Pending estimates

This amount comes from pending estimate entries in the project's primary estimate.

Estimated cost to complete

Estimate of the costs remaining for this project. The amount is calculated as follows:

Total revised estimate - Job to date costs

Estimated pct complete (%)

The amount in this field is calculated as follows:

Job to date costs / Total revised estimate

Total gross profit estimated at completion

The amount in this field is calculated as follows:

Total contract value - Total revised estimate

YTD costs

The amount in this field is calculated as follows:

The total costs from General Ledger entries for the project from the start of the current fiscal year to the WIP schedule period-end date.

Period billings

Billings for the WIP schedule period, determined as follows:

  • If there is a WIP schedule for the prior reporting period, period billings are calculated:

    Job to date billings − Job to date billings from the prior period

  • If there isn't a WIP schedule for the prior reporting period, the period billings amount is the total of billings posted in General Ledger for the WIP schedule period.
Period costs

Costs for the WIP schedule period, determined as follows:

  • If there is a WIP schedule for the prior reporting period, period costs are calculated:

    Job to date costs − Job to date costs from the prior period

  • If there isn't a WIP schedule for the prior reporting period, the period costs amount is the total of costs posted in General Ledger for the WIP schedule period.
Period earned profit

Earned profit for the WIP schedule period, determined as follows:

  • If there is a WIP schedule for the prior reporting period, period earned profit is calculated:

    Earned profit to date − Earned profit to date from the prior period

  • If there isn't a WIP schedule for the prior reporting period, no earned profit amount is shown.
Period earnings

Earnings for the WIP schedule period, determined as follows:

  • If there is a WIP schedule for the prior reporting period, period earnings is calculated:

    Earned to date − Earned to date from the prior period

  • If there isn't a WIP schedule for the prior reporting period, no earnings amount is shown.
PM forecast cost to complete

The project manager can enter a value in this field. It is automatically calculated when the project manager enters a value in the PM forecast cost at completion field or the PM forecast pct complete (%) field.

PM forecast cost at completion

You can enter an amount in this field, or it is automatically calculated if you enter a value in either of the following fields: 

  • PM forecast pct complete (%)

  • PM forecast cost to complete

PM forecast pct complete (%)

The project manager enters their estimate of how much of the project has been completed.

If the project manager has already entered an amount in the PM Forecast costs at completion field, this field is calculated as follows:

Job to date costs / PM forecast cost at completion

PM forecast contract value

The default value in this field is the value in the Total revised contract field, but you can enter a different value.

PM fields updated

The date and time that information was last updated in any of the following fields:

  • PM forecast cost to complete
  • PM forecast cost at completion
  • PM forecast pct complete (%)
  • PM forecast contract value
CFO forecast cost to complete

You can enter your forecast of the costs required to complete this project, or the amount is automatically calculated if you enter an amount in either of the following fields: 

  • CFO forecast pct complete (%)

  • CFO forecast cost at completion

CFO forecast gross profit margin pct (%)

The amount in this field is calculated as follows:

CFO forecast gross profit at completion / CFO forecast contract value

CFO forecast gross profit at completion

The amount in this field is calculated as follows:

CFO forecast contract value - CFO forecast cost at completion

CFO fields updated

The date and time that information was last updated in any of the following fields:

  • CFO forecast cost at completion
  • CFO forecast contract value
  • CFO forecast pct complete (%)
  • CFO forecast cost to complete
Cost at completion variance

The amount in this field is calculated as follows:

CFO forecast cost at completion - Total revised estimate

Contract amount variance

The amount in this field is calculated as follows:

CFO forecast contract value - Total contract value

Remaining backlog

This amount represents the work left for the project as a currency amount. The amount is calculated as follows:

CFO forecast contract value - Earned to date

Earned profit to date

The amount in this field is calculated as follows:

Earned to date - Job to date costs

Gross profit percentage of cost

The amount in this field is calculated as follows:

CFO forecast gross profit at completion / CFO forecast cost at completion

Gross profit percentage of contract

The amount in this field is calculated as follows:

CFO forecast gross profit at completion / CFO forecast contract value

Gross profit variance

The amount in this field is calculated as follows:

CFO forecast gross profit at completion - total gross profit estimated at completion

Remaining profit

This amount shows how much of the projected project remains to be earned. The amount is calculated as follows:

CFO forecast gross profit at completion - Earned profit to date

Earned profit as of end of prior year

This value comes from the end-of-year (EOY) WIP schedule from the prior year if one exists. Otherwise, the amount is zero.

The EOY WIP schedule is the WIP schedule that's created for the last reporting period of the fiscal year.

YTD earned profit

The amount in this field is calculated as follows:

Earned to date - Earned profit as of end of prior year (from the EOY WIP schedule) 

Overbilled or underbilled

If the Job to date billings amount is more or less than the Earned to date amount, this field displays the difference. Otherwise, the amount is zero.

Underbilled amounts are displayed as a positive number (for example, 10,000), overbilled amounts are displayed as a negative number (for example, −10,000).

If this field displays an amount other than zero, the same amount is displayed in the Job to date overbilled field or the Job to date underbilled field.

The amount in this field is calculated based on the whole history of the project.

Customer

The customer associated with the project.

Location

The location associated with the project.

Department

The department associated with the project.

Class

Classes can be used to create and filter project reports. Learn more about classes.

Project status

The project status can be used to prevent certain transactions from occurring, or to track projects. Learn more about project statuses.

Project type

The project type is a user-created tag that you can use to categorize and report on projects. Learn more about project types.

Project begin date

The begin date for the project. This date is specified on the Project Information page (go to Projects > All > Projects, and then select the project).

Project end date

The end date for the project. This date is specified on the Project Information page (go to Projects > All > Projects, and then select the project).

Posting preview tab

The Posting preview tab is available when you're editing an unposted WIP schedule. The summary shows the total net overbilled or underbilled amount for the projects in the WIP schedule.

The Entries section lists each project in the WIP schedule and shows the overbilling or underbilling amount for each one.

Posting summary

Descriptions of fields in the Posting summary section on the Posting preview tab
Field Description
Journal The journal to which the transaction will be posted. The posting journal is selected in the WIP management section in Configure Projects.
Description The WIP schedule's period name is used as the default description in the Post to GL window, but you can enter something different.
Reference number The reference number entered in the Post to GL window when you post the WIP schedule. This field might contain a value on the preview tab if the WIP schedule was posted and then the post was reverted.
Posting date If the WIP schedule was posted and then the post was reverted, the original posting date is shown.
Auto-reverse posting

Indicates that the posting will be automatically reversed during the next WIP schedule period.

The auto-reversal happens either at the beginning or end of the next period, depending on settings in the WIP management section of Configure Projects.

Automatic reversal date The date that the posting will be automatically reversed. The selection in the Auto-reverse WIP posting section in Configure Projects determines this date. The reversal date is either the beginning or the end of the next WIP schedule reporting period.
Accounts and values The accounts that will be debited and credited when you post the WIP schedule and the associated total amounts. These accounts are specified in Configure Projects.

Entries

Descriptions of fields in the Entries grid on the Posting preview tab
Field Description
Account

The account that will be debited or credited when the WIP schedule is posted.

Overbilled amounts are credited to the overbilling account selected in Configure Projects.

Underbilled amounts are debited to the underbilling account selected in Configure Projects.

Department The department associated with the project.
Location The location associated with the project.
Project The project name.
Class The class associated with the project.
Debit The amount that will be debited from the account.
Credit The amount that will be credited to the account.
Comment The comment entered for this project on the Overview tab.

Posting history tab

This tab lists the posting and reversal activity for the WIP schedule. Any reverted posts are also included.

Descriptions of the fields on the Posting history tab
Field Description
Journal The journal to which the schedule was posted. The posting journal is specified in the WIP management section in Configure Projects.
Journal entry number The entry number. Select this link to view he journal transaction.
Posting date The date the WIP schedule was posted.
Automatic reversal date The date that the posting will be automatically reversed. The selection in the Auto-reverse WIP posting section in Configure Projects determines this date. The reversal date is either the beginning or the end of the next WIP schedule reporting period.
Reversal Journal Number The journal number for the reversing transaction. Select this link to view he journal transaction.
Overbilling debit

The overbilling amount that was debited to the Billings in excess of costs (overbilling) account when the WIP schedule was posted.

The overbilling account is specified in the WIP management section in Configure Projects.

Overbilling credit

The overbilling amount that was credited to the Billings in excess of costs (overbilling) account when the WIP schedule was posted.

The overbilling account is specified in the WIP management section in Configure Projects.

Underbilling debit

The underbilling amount that was debited to the Costs in excess of billings (underbilling) account when the WIP schedule was posted.

The underbilling account is specified in the WIP management section in Configure Projects.

Underbilling credit

The underbilling amount that was credited to the Costs in excess of billings (underbilling) account when the WIP schedule was posted.

The underbilling account is specified in the WIP management section in Configure Projects.

Adjustment debit

The amount debited to the offset account when your post an overbilling credit or an underbilling credit.

The offset account is specified in the WIP management section in Configure Projects.

Adjustment Credit

The amount credited to the offset account when you post an overbilling debit or an underbilling debit.

The offset account is specified in the WIP management section in Configure Projects.

Description The description entered when posting the WIP schedule.