Field descriptions: WIP schedule project fields
Summary
| Field | Description |
|---|---|
| Period name | The name of the reporting period on which the WIP schedule is based. WIP schedules are based on the reporting periods set up in the top level of your company. |
| Period end | The ending date of the WIP schedule's reporting period. |
| Comment | Enter a comment about the WIP schedule. |
| End of year WIP schedule |
The end of year WIP schedule for the prior year. You can drill down to view it. If there's an end of year WIP schedule, it's used to determine YTD values in the current WIP schedule (such as YTD billed and YTD earned). If there isn't an end of year WIP schedule, YTD values are the same as job to date values. |
| State | Indicates whether the WIP schedule is posted or unposted. |
| Prior period WIP schedule |
The WIP schedule for the prior reporting period. You can drill down to view it. When you create a new WIP schedule, PM and CFO forecasts from the prior period WIP schedule are automatically copied into the new WIP schedule. If there isn't a prior period WIP schedule, PM and CFO forecasts are blank. You can always reset PM and CFO forecasts to those from the prior period using the buttons Update CFO values with CFO values from prior period and Update PM values with PM values from prior period. Values from the prior period WIP schedule are also used to determine some other values for the current period (such as Period costs and Period billings). If there is a prior period WIP schedule, the Prior period section appears and shows information from the prior period WIP schedule. |
| Last refresh |
The date and time that the WIP schedule was last updated with the latest project data and any changes to which projects are included in the WIP schedule. To get the latest project data, edit the WIP schedule, and select Refresh. When you refresh, the WIP schedule is saved automatically. |
Overview tab
The Overview tab shows the WIP projects grid. You can select multiple projects and use the buttons above the grid to update the selected projects at the same time.
Each project in the WIP projects grid shows totals for itself plus any subprojects that are included as part of it. If no subprojects are included as part of it, it shows data only for itself.
Buttons above the grid
Fields in the grid
| Field | Description |
|---|---|
| Project | The project ID and description. |
| Errors |
If there are one or more errors in the project data, the number of errors appears in this field. Select the number to view the errors. You can save the WIP schedule with errors, but you must correct the errors before posting it. |
| Warnings |
If there are one or more issues in the project's data related to the WIP schedule, the number of issues appears in this field. Select the number to view the warnings. You can save or post the WIP schedule without addressing the warnings. |
| Project manager |
The project manager assigned to the project. |
| Estimated cost to date |
This amount comes from estimate entries in the project's primary estimate. Estimate entries are included if they meet the following criteria:
|
| Total contract value |
This amount comes from all project contract lines linked to the project. The amount is the sum of the price for all project contract lines, including any change request entries linked to the project contract line through a change order. A project contract line entry is included in the calculation if it meets the following conditions:
A change request entry within the same project contract line is included in the calculation if it meets the following conditions:
|
| CFO forecast cost at completion |
You can enter an amount in this field, or it will be automatically calculated if an amount is entered in one of the following fields:
Those two fields are recalculated if an amount is entered in this field. |
| CFO forecast contract value |
Enter the forecast contract value. |
| Job to date costs |
The project's actual costs to-date. This amount comes from journal postings to the cost accounts selected in the WIP management section of Configure Projects. Journal entries are included in this amount if they meet the following conditions:
A debit amount posted to the account is added to the Job to date costs amount. A credit is subtracted. |
| Job to date billings |
This amount comes from journal postings to the revenue accounts selected in the WIP management section of Configure Projects. Journal entries are included in this amount if they meet the following conditions:
A credit amount posted to the account is added to the Job to date billed amount. A debit is subtracted. |
| CFO forecast pct complete (%) |
Enter your estimate of how much of the project has been completed. If a value has been entered in the CFO Forecast cost at completion field, this field is calculated as follows: Job to date costs / CFO forecast cost at completion |
| Earned to date |
The amount in this field is calculated as follows: CFO forecast contract value * CFO forecast pct complete (%) This amount reflects the earnings going back to the beginning of the project; it is not limited to the current year. |
| YTD billed |
The amount in this field is calculated as follows: The total revenue from General Ledger entries for the project from the start of the current fiscal year to the WIP schedule period-end date. |
| YTD earned |
The amount in this field is calculated as follows: Earned to date - Earned to date as of the end of the prior year (take from the prior year EOY WIP schedule) |
| Job to date overbilled |
If the Job to date billings amount is more than the Earned to date amount, this field displays the difference. Otherwise, the amount is zero. If this field displays an amount other than zero, the same amount is displayed in the Overbilled or underbilled field.
The amount in this field is calculated based on the whole history of the project. |
| Job to date underbilled |
If the Job to date billings amount is less than the Earned to date amount, this field displays the difference. Otherwise, the amount is zero. If this field displays an amount other than zero, the same amount is displayed in the Overbilled or underbilled field.
The amount in this field is calculated based on the whole history of the project. |
| Comment | Enter a comment about the project. |
| Finalize |
Select Yes if you have finished modifying this project. All project rows must be finalized before posting the WIP schedule. If a data refresh changes a calculated value for a project marked as Finalized, this field is automatically reset to No for that project. |
| Total revised estimate |
This amount comes from estimate entries in the project's primary estimate. Estimate entries are included if they have a workflow type of original, revision, or approved change. |
| Pending estimates |
This amount comes from pending estimate entries in the project's primary estimate. |
| Estimated cost to complete |
Estimate of the costs remaining for this project. The amount is calculated as follows: Total revised estimate - Job to date costs |
| Estimated pct complete (%) |
The amount in this field is calculated as follows: Job to date costs / Total revised estimate |
| Total gross profit estimated at completion |
The amount in this field is calculated as follows: Total contract value - Total revised estimate |
| YTD costs |
The amount in this field is calculated as follows: The total costs from General Ledger entries for the project from the start of the current fiscal year to the WIP schedule period-end date. |
| Period billings |
Billings for the WIP schedule period, determined as follows:
|
| Period costs |
Costs for the WIP schedule period, determined as follows:
|
| Period earned profit |
Earned profit for the WIP schedule period, determined as follows:
|
| Period earnings |
Earnings for the WIP schedule period, determined as follows:
|
| PM forecast cost to complete |
The project manager can enter a value in this field. It is automatically calculated when the project manager enters a value in the PM forecast cost at completion field or the PM forecast pct complete (%) field. |
| PM forecast cost at completion |
You can enter an amount in this field, or it is automatically calculated if you enter a value in either of the following fields:
|
| PM forecast pct complete (%) |
The project manager enters their estimate of how much of the project has been completed. If the project manager has already entered an amount in the PM Forecast costs at completion field, this field is calculated as follows: Job to date costs / PM forecast cost at completion |
| PM forecast contract value |
The default value in this field is the value in the Total revised contract field, but you can enter a different value. |
| PM fields updated |
The date and time that information was last updated in any of the following fields:
|
| CFO forecast cost to complete |
You can enter your forecast of the costs required to complete this project, or the amount is automatically calculated if you enter an amount in either of the following fields:
|
| CFO forecast gross profit margin pct (%) |
The amount in this field is calculated as follows: CFO forecast gross profit at completion / CFO forecast contract value |
| CFO forecast gross profit at completion |
The amount in this field is calculated as follows: CFO forecast contract value - CFO forecast cost at completion |
| CFO fields updated |
The date and time that information was last updated in any of the following fields:
|
| Cost at completion variance |
The amount in this field is calculated as follows: CFO forecast cost at completion - Total revised estimate |
| Contract amount variance |
The amount in this field is calculated as follows: CFO forecast contract value - Total contract value |
| Remaining backlog |
This amount represents the work left for the project as a currency amount. The amount is calculated as follows: CFO forecast contract value - Earned to date |
| Earned profit to date |
The amount in this field is calculated as follows: Earned to date - Job to date costs |
| Gross profit percentage of cost |
The amount in this field is calculated as follows: CFO forecast gross profit at completion / CFO forecast cost at completion |
| Gross profit percentage of contract |
The amount in this field is calculated as follows: CFO forecast gross profit at completion / CFO forecast contract value |
| Gross profit variance |
The amount in this field is calculated as follows: CFO forecast gross profit at completion - total gross profit estimated at completion |
| Remaining profit |
This amount shows how much of the projected project remains to be earned. The amount is calculated as follows: CFO forecast gross profit at completion - Earned profit to date |
| Earned profit as of end of prior year |
This value comes from the end-of-year (EOY) WIP schedule from the prior year if one exists. Otherwise, the amount is zero. The EOY WIP schedule is the WIP schedule that's created for the last reporting period of the fiscal year. |
| YTD earned profit |
The amount in this field is calculated as follows: Earned to date - Earned profit as of end of prior year (from the EOY WIP schedule) |
| Overbilled or underbilled |
If the Job to date billings amount is more or less than the Earned to date amount, this field displays the difference. Otherwise, the amount is zero. Underbilled amounts are displayed as a positive number (for example, 10,000), overbilled amounts are displayed as a negative number (for example, −10,000). If this field displays an amount other than zero, the same amount is displayed in the Job to date overbilled field or the Job to date underbilled field.
The amount in this field is calculated based on the whole history of the project. |
| Customer |
The customer associated with the project. |
| Location |
The location associated with the project. |
| Department |
The department associated with the project. |
| Class |
Classes can be used to create and filter project reports. Learn more about classes. |
| Project status |
The project status can be used to prevent certain transactions from occurring, or to track projects. Learn more about project statuses. |
| Project type |
The project type is a user-created tag that you can use to categorize and report on projects. Learn more about project types. |
| Project begin date |
The begin date for the project. This date is specified on the Project Information page (go to Projects > All > Projects, and then select the project). |
| Project end date |
The end date for the project. This date is specified on the Project Information page (go to Projects > All > Projects, and then select the project). |
Posting preview tab
The Posting preview tab is available when you're editing an unposted WIP schedule. The summary shows the total net overbilled or underbilled amount for the projects in the WIP schedule.
The Entries section lists each project in the WIP schedule and shows the overbilling or underbilling amount for each one.
Posting summary
| Field | Description |
|---|---|
| Journal | The journal to which the transaction will be posted. The posting journal is selected in the WIP management section in Configure Projects. |
| Description | The WIP schedule's period name is used as the default description in the Post to GL window, but you can enter something different. |
| Reference number | The reference number entered in the Post to GL window when you post the WIP schedule. This field might contain a value on the preview tab if the WIP schedule was posted and then the post was reverted. |
| Posting date | If the WIP schedule was posted and then the post was reverted, the original posting date is shown. |
| Auto-reverse posting |
Indicates that the posting will be automatically reversed during the next WIP schedule period. The auto-reversal happens either at the beginning or end of the next period, depending on settings in the WIP management section of Configure Projects. |
| Automatic reversal date | The date that the posting will be automatically reversed. The selection in the Auto-reverse WIP posting section in Configure Projects determines this date. The reversal date is either the beginning or the end of the next WIP schedule reporting period. |
| Accounts and values | The accounts that will be debited and credited when you post the WIP schedule and the associated total amounts. These accounts are specified in Configure Projects. |
Entries
| Field | Description |
|---|---|
| Account |
The account that will be debited or credited when the WIP schedule is posted. Overbilled amounts are credited to the overbilling account selected in Configure Projects. Underbilled amounts are debited to the underbilling account selected in Configure Projects. |
| Department | The department associated with the project. |
| Location | The location associated with the project. |
| Project | The project name. |
| Class | The class associated with the project. |
| Debit | The amount that will be debited from the account. |
| Credit | The amount that will be credited to the account. |
| Comment | The comment entered for this project on the Overview tab. |
Posting history tab
This tab lists the posting and reversal activity for the WIP schedule. Any reverted posts are also included.
| Field | Description |
|---|---|
| Journal | The journal to which the schedule was posted. The posting journal is specified in the WIP management section in Configure Projects. |
| Journal entry number | The entry number. Select this link to view he journal transaction. |
| Posting date | The date the WIP schedule was posted. |
| Automatic reversal date | The date that the posting will be automatically reversed. The selection in the Auto-reverse WIP posting section in Configure Projects determines this date. The reversal date is either the beginning or the end of the next WIP schedule reporting period. |
| Reversal Journal Number | The journal number for the reversing transaction. Select this link to view he journal transaction. |
| Overbilling debit |
The overbilling amount that was debited to the Billings in excess of costs (overbilling) account when the WIP schedule was posted. The overbilling account is specified in the WIP management section in Configure Projects. |
| Overbilling credit |
The overbilling amount that was credited to the Billings in excess of costs (overbilling) account when the WIP schedule was posted. The overbilling account is specified in the WIP management section in Configure Projects. |
| Underbilling debit |
The underbilling amount that was debited to the Costs in excess of billings (underbilling) account when the WIP schedule was posted. The underbilling account is specified in the WIP management section in Configure Projects. |
| Underbilling credit |
The underbilling amount that was credited to the Costs in excess of billings (underbilling) account when the WIP schedule was posted. The underbilling account is specified in the WIP management section in Configure Projects. |
| Adjustment debit |
The amount debited to the offset account when your post an overbilling credit or an underbilling credit. The offset account is specified in the WIP management section in Configure Projects. |
| Adjustment Credit |
The amount credited to the offset account when you post an overbilling debit or an underbilling debit. The offset account is specified in the WIP management section in Configure Projects. |
| Description | The description entered when posting the WIP schedule. |