How a checklist's on-schedule status and state are determined

There are two checklist fields that reflect the progress made toward completing a checklist in Close Workspace:

  • Checklist schedule: The following are the possible options:

    • On track

    • At risk

    • Completed

  • Checklist state: The following are the possible states.

    • Not started

    • In progress

    • Completed

Checklists also have a Status field that can be set to either Active or Inactive. That Status field is unrelated to the checklist's on-schedule status.

How the on-schedule status is determined

Whether a checklist is on schedule is determined by whether its individual tasks are on schedule. Only the status of the main task is considered. The status of the task assignments are not taken into account.

The following table shows how schedule adherence is determined for tasks. The determination is based on the current date and the task due date.

How task schedule adherence is determined

Scenario

Task not started

Task in progress

Task completed

Today is after the due date.

Overdue

Overdue

Completed

Today is before or on the due date, and task dependencies are On track or completed.

On track

On track

Completed

Today is after the due date, and the task dependencies are On track or completed.

Overdue

Overdue

Completed

Today is before or on the due date, and the task dependencies are overdue.

At risk

At risk

Completed

Today after the due date, and task dependencies are overdue.

Overdue

Overdue

Completed

Today is before or on the due date, and the task dependencies are at-risk.

On track

On track

Completed

Today after the due date, and the task dependencies are at-risk.

Overdue

Overdue

Completed

The following table shows how the on-schedule status of the tasks affects the on-schedule status of the checklist.

How the on-schedule status of tasks affects checklists
Tasks' on-schedule status Checklist on-schedule status Notes

All tasks are completed.

Completed

All task work is finished.

One or more tasks are at-risk.

At risk

Indicates that at least one dependent task is overdue.

One or more tasks are overdue. No task is at risk.

At risk

At the checklist level, overdue tasks are reflected as at-risk.

Tasks are either not started or in progress, and all are on track

On track

No delay or risk detected.

Tasks are either in progress, at risk, or not started.

At risk

An at risk status overrides other tasks being on track and not started.

One task is at risk and the others are completed.

At risk

A single at-risk task affects the overall checklist status.

One task is overdue, and the others are completed.

At risk

Even one overdue task causes the checklist to be at risk.

How the state is determined

The state of the individual tasks included in the checklist determines the state of the checklist. The state of task assignments determines the state of the associated task.

The following table describes how task states and user actions affect the checklist state.

How tasks states affect the checklist state

Action or condition

Task assignments

Task

Checklist state

Intacct behavior

All task assignments are not started.

Not started

Not started

Not started

Task reflects the states of the task assignments

Any one task assignment is marked as in progress.

Mixed

In progress

In progress

Task is automatically updated to In progress

All task assignments are completed.

Completed

Completed

Completed

Task is automatically updated to Completed

Task is marked completed manually.

Completed

Completed

Based on task states

Task assignments are automatically changed to Completed

A completed task assignment is reopened (set to in progress).

Mixed

In progress

In progress

Task status is automatically updated to In progress

Task is reopened manually (set to in progress).

In progress

In progress

Based on task states

Task assignments are automatically changed to In progress

The checklist tasks are all not started.

Not started

Not started

Not started

Checklist state reflects the aggregate task states

Regional availability

Close Workspace is available in the following regions:

  • Canada

  • United Kingdom

  • United States