Release retainage when generating project contract invoices

Generate project contract invoices to release and include billed retainage amounts as part of your regular project contract billing.

Construction subscription is needed. To enable a Construction subscription, contact your Sage Intacct account manager. Regional support for Construction is limited to the United States, Canada, Australia, and the United Kingdom.

This task releases retainage previously withheld on project contracts only. It combines the released retainage and regular project contract billing on the same invoice.

You can release up to the full amount of retainage previously held for each Construction project contract line.

When you release or bill retainage by generating a project contract invoice, Sage Intacct creates three invoices:

  • Project contract invoice: Shows the retainage billed for each Construction project contract line.

  • AR retainage release invoice: Records the release of retained amounts.

  • AR credit retainage release invoice: Offsets the released retainage in Accounts Receivable.

You can also release retainage using the Retainage task on the Accounts Receivable or Projects menu, or in bulk using the flexible retainage release feature.
  1. When you configure Accounts Receivable (Accounts Receivable > Setup > Configuration), specify a retainage release clearing account. This clearing account is used when you release and bill retainage amounts related to Construction project contract invoices.

  2. When generating project contract invoices (Projects > All> Invoices > Generate Invoices), specify the following:

    1. On the Invoicing options tab, select to Invoice by project contract. Then select a project contract.

    2. Complete the remaining fields on this tab, and select Preview.

    You can only release retainage amounts on Construction project contract invoices.
  3. For progress bill Construction project contract lines:

    1. Scroll to the Project contract lines section of the Generate invoices page.

    2. In the Retainage to bill this period column, enter the retainage amount to bill for each project contract line.

  4. For time and material Construction project contract lines:

    1. Scroll to the Summary - selected time and material expense section.

    2. In the Retainage to bill this period column, enter the retainage amount to bill for each project contract line.

  5. Review and complete the other fields on the page as needed. Then create the invoice.